Waka Kotahi NZ Transport Agency has confirmed that State Highway 25A between Kōpū and Hikuai will be re-open to traffic in time for Christmas – a full three months earlier than anticipated.
Waka Kotahi NZ Transport Agency Waikato/Bay of Plenty infrastructure delivery regional manager Jo Wilton says the route will re-open by December 20, 2023, now that the decking is complete on the new 124 metre bridge, which spans the abyss that severed the highway in late January.
“Our team has done an amazing job, not only constructing the new bridge in record time, but at the same time we’ve invested an additional $25m to enable multiple crews to clear slips, replace the original undersized culvert, and undertake crucial road maintenance work along the rest of the length of SH25A to ensure the whole corridor is up to scratch, safe and more resilient.
“Getting this maintenance work completed now also means we can avoid further work and disruption for drivers during the busy summer period.”
The new Taparahi Bridge on State Highway 25A between Kōpū and Hikuai has been constructed in less than seven months after the road was washed away by severe weather earlier this year.
Jo says while there is still a lot of work to do to finish the bridge by Christmas, getting traffic across as soon as possible has always been the aim for Waka Kotahi.
“We’re thrilled to be able to announce that the two sides of the Coromandel Peninsula will be reconnected once again in time for the summer holidays, with traffic able to cross the SH25A bridge by December 20.
“We know how difficult the highway closure has been on local families, businesses, schools and communities and the impact it’s had on visitors to the region. That’s why, along with our builders, McConnell Dowell and Fulton Hogan JV, we’ve pulled out all the stops to deliver the fastest and most resilient solution for the Coromandel.
“With the build beginning in June, getting it open in less than seven months is a huge achievement given a bridge of this type would normally take 12 to 14 months to construct.
“We’ve built the bridge in record time by accelerating our work programme, with teams working 24 hour shifts both on site and offsite at Eastbridge in Napier, where the steel girders were manufactured.
“In addition, we used a bridge design we already had and repurposed steel plates which had been purchased for the Minden bridge on Tauranga’s Takitimu North Link project, meaning we didn’t have a lengthy wait for steel to come in from overseas.”
With finishing works still ongoing, the bridge will open under traffic management at a reduced speed. The project team will be completing drainage and planting, so the project won’t be fully complete for a few more months.
This work won’t require the road to be closed, though traffic management will be required from time to time.
The cost of the bridge, once everything is finished, is expected to be approximately $43m, under the $50m estimate.
“We’d like to thank everyone who is working so hard to get this bridge open by Christmas and our special thanks to the Coromandel community for their patience and support. We know it’s been a tough year and we hope this new bridge is the gift that helps get the Peninsula back on its feet.”
2 comments
Look Commissioners
Posted on 14-11-2023 08:26 | By Yadick
Infrastructure completed, land stabilized, bridge constructed, road open in 7 months whoa to go, under time, under budget.
You could learn a lot of lessons here instead of lavishing yourselves in monetary cream while bleeding the tax payer of every cent you possibly can, disrupting the entire traffic flow of Tauranga and causing grief, pain and misery for our once bustling hospitality industry.
Perhaps you could bring some festive cheer this Christmas and decorate all the roadcones as miniature Christmas trees - bah humbugs
Amazing
Posted on 14-11-2023 08:28 | By Wigan
2 things stand out here. "Ahead of schedule" and "Under budget" Well done to all concerned. This just shows what can be done when people have a mind to achieve. Compare to the "dogs breakfast" in Tauranga. I can't remember when there was not roadworks on Cameron Road and just checked back on Sunlive, 800M of cycle path from Wairoa River to Bethlehem was started in March! I shudder to think how much all this has cost in construction $s and lost/defunct business'
Leave a Comment
You must be logged in to make a comment.