NZTA Waka Kotahi are asking motorists travelling on State Highway 2 in the Waihī to Tauranga corridor to be mindful and aware of the planned road works programme for the week starting March 18, 2024
"While we aim to do this work with as little disruption as possible, we know that roadworks can be inconvenient. Thanks for your patience while we do these important works," says an NZTA spokeserson.
"Please drive carefully through work sites and stick to the temporary speed limits. Our programme is weather dependent, so may be postponed to the next suitable day/night."
Well maintained roads are an important part of keeping people safe.
Intended programme for March 18 to 25
Location |
Type of work |
Schedule |
Maintenance / remaining reseal sites |
There are no reseal sites programmed for this week. Remaining sites to be completed from w/c 26 March are listed below.
|
Nightworks under stop/go. Temporary speed limits on the following day with loose chip. Estimated completion of reseal programme early April. |
Athenree Gorge
|
As part of the safety improvements project between Waihī and Ōmokoroa, 3.8km of flexible median barrier is being installed north of Katikati, through the Athenree Gorge. Widening work has previously taken place at this location, and installation of median barrier has been coordinated with the reseals programme on SH2 this summer. Contra flow in place with speed restrictions. |
In progress, estimated completion April 2024 |
Kauri Point Road to Stokes Road
|
Service relocations underway. Contraflow and shoulder closures in place with speed restrictions. |
In progress |
SH2/Sharp Road Intersection
|
Roundabout construction underway with significant activities. Night works stop/go for concrete and barrier works. There will also be daytime intermittent stop/go traffic management in place which may cause longer delays, but typically expect minor delays of one to two minutes. |
Ongoing to mid-2024 |
Apata Curves
|
Road widening works underway, these are enabling works for roundabout construction. Contraflow in place with speed restrictions. There will be intermittent stop/go traffic management in place which may cause longer delays, but typically expect minor delays. |
Enabling works for roundabout site estimated completion 2025 |
SH2/Ōmokoroa Road |
Shoulder closures in place with speed reduction for early works. |
In progress |
SH2 Te Puna / Loop Road, Ainsworth Road |
Powerline removal, and underground drilling for upgrades will take place between Loop Road and Ainsworth Road, at times both lanes will be held for 2 minutes at a stop/stop while this work is done. Delays are to be expected. |
Saturday 16 March |
SH2/Te Mete Road, Te Puna
|
Haul road set up to support summer earthworks season for construction of Takitimu North Link, shoulder closure, 60km/h temporary speed limit. |
Ongoing |
SH2/Fifteenth Ave |
Early works underway at SH2/Fifteenth Ave where an on-ramp bridge connection will be built as part of the Takitimu North Link project. Tree felling will take place on with a shoulder closure in place from the Cameron Road intersection onto SH2. |
Thursday 21 to Saturday 23 March (7.30am – 6pm) |